Question: 25. You have 8 activities in your project whose names and durations are as follows: A 3, B 4, C 11, D 7, E 5,

25.

You have 8 activities in your project whose names and durations are as follows: A 3, B 4, C 11, D 7, E 5, F 4, G 13, and H 5. Activity A has three immediate successors: B, E, and G. Activity B is followed by Activity C. Activity C is followed by Activity D. Activity E is followed by Activity F. Activity F is followed by Activity D. Activity G is followed by Activity H. Activity H is followed by Activity D. What is the duration of the project's critical path?

Group of answer choices

1.25

2.19

3.32

4.28