A construction project has indirect costs totalling $40,000 per week Major activities in the project and their
Question:
Crashing costs for each activity are:
a. Determine the minimum-cost crashing plan that will take off six weeks from the project duration.
b. Plot the total cost curve against project duration. What is the optimum number of weeks to crash the project?