Question: A construction project has indirect costs totalling $40,000 per week Major activities in the project and their expected durations are shown in the following precedence
-1.png)
Crashing costs for each activity are:
-2.png)
a. Determine the minimum-cost crashing plan that will take off six weeks from the project duration.
b. Plot the total cost curve against project duration. What is the optimum number of weeks to crash the project?
9 8 2 2 8-2 3 1 Crashing Costs ($000) Second Week Activity First Week Third Week $18 24 30 15 30 12 $22 25 30 20 25 35 36 26 24 40 40 7 10 10 26 10 15 25 12 13 15
Step by Step Solution
3.26 Rating (161 Votes )
There are 3 Steps involved in it
a Weeks Crashed Path 0 1 2 3 4 5 6 12349 35 wk 34 33 32 31 30 29 ... View full answer