Question: 26) [15 points] Suppose you have a project with the following failure characteristics: Impact (0-1) 0.5 Potential Consequence Significant cost over-run Significant schedule slippage Performance
26) [15 points] Suppose you have a project with the following failure characteristics: Impact (0-1) 0.5 Potential Consequence Significant cost over-run Significant schedule slippage Performance not per contract Law suit Potential Problem Likelihood (0-1) Key Team Member Leaves 0.3 Required technology unavailable Equipment failure Subcontractor goes out of business Required permits not obtained 0.2 0.5 0.7 0.2 0.2 0.3 0.1 a) Compute an overall risk factor for this project. (You must show all computations to receive credit). Ans: b) Would you classify this as a "risky" project? Why or why not? Ans: