Question: 26 (Activity A: Duration = 2, predecessor = none), (Activity B: Duration = 5, predecessor = A), (Activity C: Duration = 6, predecessor = B),

26 (Activity A: Duration = 2, predecessor =

26 (Activity A: Duration = 2, predecessor = none), (Activity B: Duration = 5, predecessor = A), (Activity C: Duration = 6, predecessor = B), (Activity D: Duration = 7, predecessor = B), (Activity E: Duration = 4, predecessor = C,D). Crashable Activities (C: 2 days max, D: 2 days max) Crashing cost per day (C: 400$, D: 700$) Total crashing cost will be ($): * (1.5 Points) 700 1800 1100 2200 None of the others