Question: 27 = (Activity A: Duration = 2, predecessor none), (Activity B: Duration = 5, predecessor = A), (Activity C: Duration = 6, predecessor = B),

27 = (Activity A: Duration = 2, predecessor

27 = (Activity A: Duration = 2, predecessor none), (Activity B: Duration = 5, predecessor = A), (Activity C: Duration = 6, predecessor = B), (Activity D: Duration = 7, predecessor = B), (Activity E: Duration = 4, predecessor = C,D). Crashable Activities (C: 2 days max, D: 2 days max) Crashing cost per day (C: 400$, D: 700$) Project duration after crashing will be: (1.5 Points) 14 15 16 17 None of the others