Question: 26. Your project schedule has an activity node with the following data elements and values: Early Start=5, Duration=3, Early Finish=7, Late Start=13, Late Finish=15. Given

26.

Your project schedule has an activity node with the following data elements and values: Early Start=5, Duration=3, Early Finish=7, Late Start=13, Late Finish=15. Given this information, what value should be in this activity node's Total Float field?

Group of answer choices

1.0

2.2

3.8

4.3