Question: 26. Your project schedule has an activity node with the following data elements and values: Early Start=5, Duration=3, Early Finish=7, Late Start=13, Late Finish=15. Given
26.
Your project schedule has an activity node with the following data elements and values: Early Start=5, Duration=3, Early Finish=7, Late Start=13, Late Finish=15. Given this information, what value should be in this activity node's Total Float field?
Group of answer choices
1.0
2.2
3.8
4.3