Question: 2a) b) A local project being analyzed by PERT has 11 activities, 9 of which are on the critical path. If the estimated time along

2a) 2a) b) A local project being analyzed by PERT has
b)
2a) b) A local project being analyzed by PERT has
A local project being analyzed by PERT has 11 activities, 9 of which are on the critical path. If the estimated time along the critical path is 105 days with a project variance of 25, what is the probability that the project will be completed in 110 days or less? (please answer to four decimal digits) Your Answer: 21 A project whose critical path has an estimated time of 50 days with a variance of 100 has a 25% chance that the project will be completed before day (please round off to two decimal digits) Your

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!