Question: A local project being analyzed by PERT has 15 activities, 9 of which are on the critical path. If the estimated time along the critical

A local project being analyzed by PERT has 15 activities, 9 of which are on the critical path. If the estimated time along the critical path is 105 days with a project variance of 25 , what is the probability that the project will be completed in 100 days or less? (please answer to four decimal places) Your Answer: Your Answer Question 21 (1 point) A local project being analyzed by PERT has 13 activities, 5 of which are on the critical path. If the estimated time along the critical path is 105 days with a project variance of 25 , what is the probability that the project will be completed in 110 days or less? (please answer to four decimal digits) Your