Question: [ 3 0 points ] Activities' optimistic ( a ) , most likely ( m ) , and pessimistic ( b ) times in weeks
points Activities' optimistic a most likely m and pessimistic b times in weeks for a
small project are shown in the table below:
See image provided
a points Draw the network and show the forward pass ES and EF and calculate the Total
Expected Project Duration TE
b points What is the probability of completing the project in weeks?
c points Calculate the number of weeks to complete the project based on a
probability.
d points What is the of risk associated with an assumed completion time of
weeks?
e points What is the optimistic completion time for the project?
f points What is the pessimistic completion time for the project? points Activities' optimistic a most likely boldsymbolm and pessimistic b times in weeks for a small project are shown in the table below:
a points Draw the network and show the forward pass ES and EF and calculate the Total Expected Project Duration boldsymbolTboldsymbolE
b points What is the probability of completing the project in weeks?
c points Calculate the number of weeks to complete the project based on a probability.
d points What is the of risk associated with an assumed completion time of weeks?
e points What is the optimistic completion time for the project?
f points What is the pessimistic completion time for the project?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock