Question: [ 3 0 points ] Activities' optimistic ( a ) , most likely ( m ) , and pessimistic ( b ) times in weeks

[30 points] Activities' optimistic (a), most likely (m), and pessimistic (b) times in weeks for a
small project are shown in the table below:
*See image provided
a.[10 points] Draw the network and show the forward pass (ES and EF) and calculate the Total
Expected Project Duration TE?.
b.[4 points] What is the probability of completing the project in 33 weeks?
c.[4 points] Calculate the number of weeks to complete the project based on a 42%
probability.
d.[4 points] What is the % of risk associated with an assumed completion time of 28
weeks?
e.[4 points] What is the optimistic completion time for the project?
f.[4 points] What is the pessimistic completion time for the project? 3)[30 points] Activities' optimistic (a), most likely (\(\boldsymbol{m}\)), and pessimistic (b) times in weeks for a small project are shown in the table below:
a.[10 points] Draw the network and show the forward pass (ES and EF) and calculate the Total Expected Project Duration \(\boldsymbol{T}_{\boldsymbol{E}}\)?
b.[4 points] What is the probability of completing the project in 33 weeks?
c.[4 points] Calculate the number of weeks to complete the project based on a \(42\%\) probability.
d.[4 points] What is the \(\%\) of risk associated with an assumed completion time of 28 weeks?
e.[4 points] What is the optimistic completion time for the project?
f.[4 points] What is the pessimistic completion time for the project?
[ 3 0 points ] Activities' optimistic ( a ) ,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!