Question: View Policies Current Attempt in Progress Using the following project information, calculate the variance for each of the project activities. Optimistic Time Most Likely Time




View Policies Current Attempt in Progress Using the following project information, calculate the variance for each of the project activities. Optimistic Time Most Likely Time Pessimistic Time Immediate Activity Estimate(weeks) Estimates (weeks) Estimates (weeks) Predecessor(s) A 2 3 5 none B 2.5 4 5 A C 5 7 8 A D 3 5 7 B,C E 3 6 14 B,C F 2 5 8 D G 4 5 6 E H 6 6 8 F | 5 8 10 G
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
