Question: ( 3 0 points, plus 1 5 points possible extra credit ) Heretofore w e have used a formula t o compute the schedule score
points, plus points possible extra credit Heretofore have used a formula compute
the schedule score the negative the IPQ value divided the average fab out rate over the
target cycle time fab out plus one shift. This exact the target fab outs are constant over
this time, but approximation otherwise. Suppose wish refine the computation the
schedule score more precisely account for a timevarying fab out rate. The schedule score
should express how many days early late the fab out schedule would the downstream WIP
the end the upcoming shift more WIP a particular productstep processed
during the shift.
Assume the target fab out schedule characterized a constant target rate for each product
each work week, possibly changing rate the workweek boundaries. For simplicity
exposition, assume line yields.
Initially, consider the computation ideal production quantities and schedule scores the
start a production shift. have the following set:
Notation
Indices
i work week. assume the first work week fabout commits numbered
product
process step; denotes the last process step for fabricating product
Parameters
actual WIP product step
actual WIP product downstream from step
time days from now until the end week dots, must least large the longest target cycle time for any product. set The value could dots, depending where the
week the upcoming production shift lies. The value will the second
work week has days the value will and
For a given let denote the largest value i such that fol falls work week
fol unfulfilled fabout commits week i for product These commits express desired wafer
trackouts product from step allow for the case that different weeks have different fab
out targets for product assume target output a uniform rate over the work week.
cumulative target fabouts, expressed wafers, for product due time end
week Note that simply the sum weekly target fab outs through week
For convenience, set
the total target cycle time days from completion step product
the completion step
Variables computed
the ideal production quantity the upcoming shift for step product
the number days early positive late negative production step product
will the end the shift wafers are tracked out step the upcoming shift.
points For the assumption constant target output rates within each work week, express
the cumulative target fabouts due arbitrary point continuous time days points Consider the figure below. Add dotted lines show the vertical axis and
show the horizontal axis. Explain.
points Provide formulas compute and precisely. You may assume target fab
outs for product are positive every week.
points lots are dispatched during the shift, the IPQ should updated. Suppose a wafer
quantity step the process flow fabricate product dispatched. How should the
values and updated?
points For a dispatch wafers above, how should the schedule score
updated?
points extra credit hard there are one more weeks which there output
commitment for product then the cumulative target output curve will have "flat spots"
When located along such a flat spot the cumulative target output
curve, ambiguity arises expressing how late how early the production date. Provide
a procedure compute the schedule score this case, and explain how should updated
after a dispatch
and fractions thereof from the start the upcoming shift follows:
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
