Question: ( 3 0 points, plus 1 5 points possible extra credit ) Heretofore w e have used a formula t o compute the schedule score

(30 points, plus 15 points possible extra credit) Heretofore we have used a formula to compute
the schedule score as the negative of the IPQ value divided by the average fab out rate over the
target cycle time to fab out plus one shift. This is exact if the target fab outs are constant over
this time, but an approximation otherwise. Suppose we wish to refine the computation of the
schedule score to more precisely account for a time-varying fab out rate. The schedule score
should express how many days early or late to the fab out schedule would the downstream WIP
beat the end of the upcoming shift ifno more WIP of a particular product-step is processed
during the shift.
Assume the target fab out schedule is characterized by a constant target rate for each product in
each work week, possibly changing rate at the work-week boundaries. For simplicity of
exposition, assume 100% line yields.
Initially, we consider the computation of ideal production quantities and schedule scores at the
start of a production shift. We have the following set-up:
Notation
Indices
i work week. We assume the first work week of fab-out commits is numbered i=1.
l product
j process step; jl denotes the last process step for fabricating product l
Parameters
AWlj= actual WIP of product lat step j
ADWlj=k=J+1jlAWlk= actual WIP of product l downstream from step j
ti= time in days from now (time0) until the end of week i,i=1,2,3,dots,ItI must beat least as large as the longest target cycle time for any product.t0is set to0. The value oft1 could be0.5,1,1.5,2,dots,6.5,or7, depending on where in the
week the upcoming production shift lies. The value oft2 will bet1+7(assuming the second
work week has 7 days), the value oft3 will bet1+14, and soon.
For a given t, let i-(t) denote the largest value of i such that ti+1fol(i)=illjllFOl(ti)=ltiiFOl(ti)iFOl(ti)=k=1ifol(tk)FOl(t0)=0TCTFOlj=jljlIPQlj=jlSSlj=jljtti,i.e.,t falls in work week i+1.
fol(i)= unfulfilled fab-out commits in week i for product l. These commits express desired wafer
track-outs of product l from step jl.We allow for the case that different weeks have different fab-
out targets for product l.We assume target output isat a uniform rate over the work week.
FOl(ti)= cumulative target fab-outs, expressed in wafers, for product l due by time ti(the end of
week i). Note that FOl(ti)is simply the sum of weekly target fab outs up through week i,i.e.,
FOl(ti)=k=1ifol(tk)
For convenience, set FOl(t0)=0.
TCTFOlj= the total target cycle time (expressedin days) from completion of step jon product l
to the completion of step jl.
Variables (tobe computed)
IPQlj= the ideal production quantity in the upcoming shift for step jon product l
SSlj= the number of days early (if positive)or late (if negative) production at step jon product l
will beat the end of the shift ifno wafers are tracked out of step jin the upcoming shift.
(a)(5 points) For the assumption of constant target output rates within each work week, express
the cumulative target fab-outs due atan arbitrary point tin continuous time (measuredin days (b)(5 points) Consider the figure below. Add dotted lines to show IPQljon the vertical axis and
to show -SSljon the horizontal axis. Explain.
(c)(10 points) Provide formulas to compute IPQlj and SSlj precisely. You may assume target fab
outs for product l are positive in every week.
(d)(5 points)As lots are dispatched during the shift, the IPQ should be updated. Suppose a wafer
quantity Wljof step iin the process flow to fabricate product lis dispatched. How should the
values ofIPQlj,AWlj, and ADWljbe updated?
(e)(5 points) For a dispatch ofWlj wafers as above, how should the schedule score SSljbe
updated?
(e)(15 points extra credit - hard)If there are one or more weeks in which there isno output
commitment for product l, then the cumulative target output curve will have "flat spots" init.
When ADWljor(TCTFOlj+0.5)is located along such a flat spot in the cumulative target output
curve, ambiguity arises asto expressing how late or how early is the production to date. Provide
a procedure to compute the schedule score in this case, and explain how it should be updated
after a dispatch
and fractions thereof from the start of the upcoming shift)as follows:
( 3 0 points, plus 1 5 points possible extra

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!