Question: 3 . 1 For the Baynes hydroelectric project, for which you are one of the project managers, you have to keep control over the cost

3.1 For the Baynes hydroelectric project, for which you are one of the project managers, you have to keep control over the cost of the project phase. Phase 1 will take six years to complete and you are three years into it. The partial structure of Phase 1 is as follows:
For A and for B , which are sub-accounts of the Phase 1 account, you have the following information:
\table[[\table[[Project],[Sub-],[Account]],BCAC,ACWP,BQAC,AQWP,\table[[Percentage],[complete],[(%)