LEARNING OBJECTIVE: Differentiate between the methods used to visually display project schedules.
A network diagram for a project is different from a Gantt chart for a project in which of the following ways?
a A network diagram is better for comparing relationships among project activities.
b A network diagram is the basis for creating a risk management plan.
c A network diagram is used to display all of the project work.
d A network diagram is the basis for creating the project schedule.
Correct