LEARNING OBJECTIVE: Differentiate between the methods used to visually display project schedules.
A network diagram for a project is different from a Gantt chart for a project in which of the following ways?
a.) A network diagram is better for comparing relationships among project activities.
b.) A network diagram is the basis for creating a risk management plan.
c.) A network diagram is used to display all of the project work.
d.) A network diagram is the basis for creating the project schedule.
Correct
 3:20 .1I 5G 48 LEARNING OBJECTIVE: Differentiate between the methods used

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Programming Questions!