Question: 3 . 2 0 Development of Version 2 . 0 of a particular accounting software product is being considered by Jose Noguera's technology firm in
Development of Version of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table:
begintabularcccccc
hline & begintabularc
NORMAL
TIME
WEESS
endtabular & begintabularc
CRASH
TIME
WEEKS
endtabular & begintabularc
NORMAL
COST
endtabular & begintabularc
CRASH
COST
endtabular & begintabularc
IMMEDIATE
PREDECESSORS
endtabular
hline ACTIVITY & & & $ & $ &
hline B & & & & &
hline C & & & & &
hline D & & & & & A
hline E & & & & & B
hline F & & & & & C
hline G & & & & & D E
hline
endtabular
a What is the project completion date?
b What is the total cost required for completing this project on normal time?
c If you wish to reduce the time required to complete this project by week, which activity should be crashed, and how much will this increase the total cost?
d What is the maximum time that can be crashed? How much would costs increase?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock