Question: 3) (20%) Using the information given, do the following: Time Immediate Immediate Predecessor Activity (weeks) Activity Predecessor A 2 F --- C, D B 4

3) (20%) Using the information given, do the following: Time Immediate Immediate Predecessor Activity (weeks) Activity Predecessor A 2 F --- C, D B 4 --- G E C A 1 H E, F D B 1 I G E B 5 J H, I a) (7%) Construct an activity-on-arrow (AOA) precedence diagram. b) (7%) What is the critical path? What is the expected length of the project? c) (6%) What is the slack time of each activity? Time (weeks) 236N 8