Question: 3) (20%) Using the information given, do the following: Time Immediate Immediate Predecessor Activity (weeks) Activity Predecessor A 2 F --- C, D B 4

3) (20%) Using the information given, do the

3) (20%) Using the information given, do the following: Time Immediate Immediate Predecessor Activity (weeks) Activity Predecessor A 2 F --- C, D B 4 --- G E C A 1 H E, F D B 1 I G E B 5 J H, I a) (7%) Construct an activity-on-arrow (AOA) precedence diagram. b) (7%) What is the critical path? What is the expected length of the project? c) (6%) What is the slack time of each activity? Time (weeks) 236N 8

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!