Question: 3 3 Software Development Specialists ( SDS ) is in - volved with developing software for customers in the banking industry. SDS breaks a large
Software Development Specialists SDS is in volved with developing software for customers in the banking industry. SDS breaks a large program ming project into teams that perform the necessary steps. Team A is responsible for going from general systems design all the way through to actual systems testing. This involves separate activities. Team B is then responsible for the final installation.
To determine cost and time factors, optimistic, most likely, and pessimistic time estimates have been made for all of the activities involved for team A
The first step that this team performs is general sys tems design. The optimistic, most likely, and pessi mistic times are and weeks. Following this, a number of activities can begin. Activity is involved with procedures design. Optimistic, most likely, and pessimistic times for completing this activity are and weeks. Activity is developing detailed report designs. Optimistic, most likely, and pessimis tic time estimates are and weeks. Activity detailed forms design, has optimistic, most likely, and pessimistic time estimates of and weeks.
Activities and involve writing detailed pro gram specifications and developing file specifications. The three time estimates for activity are and weeks, and the three time estimates for activity are and weeks. Activity involves specifying system test data. Before this is done, activity involv ing file specifications, must be completed. The time estimates for activity are and weeks. Activity involves reviewing forms. Before activity can be conducted, detailed forms design must be completed. The time estimates for activity are and weeks. The next activity, activity is reviewing the detailed report design. This requires that the detailed report design, activity be completed first. The time esti mates for activity are and weeks, respectively.
Activity involves reviewing procedures de sign. Time estimates are and weeks. Of course, procedures design must be done before activity can be started. Activity involves the system de sign checkpoint review. A number of activities must be completed before this is done. These activities include reviewing the forms, reviewing the detailed report design, reviewing the procedures design, writ ing detailed program specs, and specifying system test data. The optimistic, most likely, and pessimistic time estimates for activity are and weeks. Performing program logic design is activity This can be started only after the system design checkpoint review is completed. The time estimates for activity are and weeks.
Activity coding the programs, is done only after the program logic design is completed. The time estimates for this activity are and weeks. Ac tivity is involved in developing test programs. Activ ity is the immediate predecessor. Time estimates for activity are and weeks. Developing a system test plan is activity A number of activities must be completed before activity can be started. These ac tivities include specifying system test data, writing de tailed program specifications, and reviewing procedure designs, the detailed report design, and forms. The time estimates for activity are and weeks.
Activity creating system test data, has time estimates of and weeks. Activity must be done before activity can be started. Activity is reviewing program test results. The immedi ate predecessor to activity is to test the programs activity The three time estimates for activity are and weeks. The final activity is conducting system tests. This is activity Before activity can be started, activities and must be complete. The three time estimates for conducting these system tests are and weeks.
How long will it take for team A to complete its programming assignment?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock