Question: 3 4 . Baseline Performance: A cost performance index ( CPI ) of 0 . 8 9 means the project is spending behind plan by

34. Baseline Performance: A cost performance index (CPI) of 0.89 means the project is spending behind plan by 11%. Thus, CPI represents a measure that indicates
a. Project spending is only progressing as planned, but no better.
b. How efficiently work is being performed with regard to the budgeted cost of work.
c. The project is gladly reporting it is only getting 89 cents out of every dollar invested.
d. The project is experiencing a significant cost under run.
e. The cost baseline is likely inaccurate by 11%.
Know value & meaning: <1.0= earned less than planned >1.0 earned more than planned

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!