Question: 3 . ( 4 pts ) Net requirements for a lot - sizing problem are ( 1 0 0 , 8 0 , 7 5

3.(4 pts) Net requirements for a lot-sizing problem are (100,80,75,120,110,100,90,80). Setup cost is
$250, and holding cost is $1.20. You can use the table below to structure your answers for part (a),(b),
and (c).
(a)(0.5 pts) Determine the single-lot (SL) and lot-for-lot (LFL) release plans (sizes and periods) and
the cost of each.
(b)(0.5 pts) Determine the lot release plan and cost using EOQ.
(c)(1 pt) Determine the lot release plan and cost using dynamic lot-sizing with EOQ=198 and the
Wagner Whitin property.
(d)(1.5 pts) Determine the cost of the optimal plan using the tabular method. You can use the
table below to structure your solution to this part and part (e).
(e)(0.5pts Determine the optimal lot release plan and verify that the corresponding total cost
(setup costs plus inventory holding costs) is consistent with the result from Part (d).
 3.(4 pts) Net requirements for a lot-sizing problem are (100,80,75,120,110,100,90,80). Setup

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!