Question: 3 - 5 . Lucas developed a project crashing data table for the I - 8 0 repair project as shown below. The current estimated

3-5. Lucas developed a project crashing data table for the I-80 repair project as shown below. The current estimated total cost for the project is $ 1,000,000 Indirect cost for the project is $ 10,000 per week. Use expected task times as normal times to answer questions and assume that there is no uncertainty for task times.
3. If Lucas would like to minimize the total project cost by crashing, (1) what is the project length after crashing? (2) what is the total project cost after crashing?
4. If Lucas would like to minimize the project duration by crashing as long as the total project cost does not exceed $ 1,000,000,(1) what is the project length after crashing? (2) what is the total project cost after crashing?
5. If Lucas would like to minimize the project duration by crashing, (1) what is the project length after crashing? (2) what is the total project cost after crashing?
 3-5. Lucas developed a project crashing data table for the I-80

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!