Question: A project crashing data table for the system project is shown below. Crash time is the absolute minimum time to do that task. How much
A project crashing data table for the system project is shown below. Crash time is the absolute minimum time to do that task. How much will it cost to crash the project by 5 weeks?
| Task | Time to Complete (weeks) | Crash Time (weeks) | Cost per Week to Crash |
| A | 8 | 7 | $11,000 |
| B | 6 | 2 | $6,500 |
| C | 4 | 1 | $7,000 |
| D | 3 | 2 | $5,000 |
| E | 6 | 5 | $4,000 |
| F | 4 | 1 | $8,000 |
| G | 4 | 1 | $10,000 |
| H | 3 | 1 | $9,000 |