Question: 3 7 0 0 : 1 0 : 4 8 Consider the following table of activities that describes a project network. Without causing the critical

3700:10:48Consider the following table of activities that describes a project network. Without causing the critical path to become noncritical or otherwise wastingmoney, by how many days could you reduce the first activity that you would crash?ActivityBCDEFGPredecessorsAAB, CB, CB, CD, E, FNormalduration(days)56105Crashduration(days)B543564Normal cost$1,000$4,000$2,000$1,000$5,000$3,000$2,000Crash cost$4,000$7,000$4,000$2,000$8,000$5,000$5,000
 3700:10:48Consider the following table of activities that describes a project network.