Question: 3 . 7 Using AOA, diagram the network described below for Lillian Fok's construction project. Calculate its critical path and project completion time. table

3.7 Using AOA, diagram the network described below for Lillian Fok's construction project. Calculate its critical path and project completion time.
\table[[ACTIVITY,NODES,\table[[TIME],[(WEEKS)]],ACTIVITY,NODES,\table[[TIME],[(WEEKS)]]],[J,1-2,10,N,3-4,2],[K,1-3,8,0,4-5,7],[L,2-4,6,P,3-5,5],[M,2-3,3,,,]]