Question: 3 7 . Which process is concerned with providing forecasts to update current cost information? a . Monitor and Control Project Work b . Project
Which process is concerned with providing forecasts to update current cost information?
a Monitor and Control Project Work
b Project Management Information System
c Close Project or Phase
d Direct and Manage Project Work