Question: 3 . 8 Draw the AON ( activity on node ) project network chart complete with ES , EF , LS , LF , and
Draw the AON activity on node project network chart complete with ES EF LS LF and Slack on the project activity nodes points
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
a
a Develop an AON network for this problem.
b What is the critical path?
c What is the total project completion time?
d What is the slack time for each individual activity?