Question: Activity Immediate Predecessor ( s ) Time ( Days ) A - - 3 B A 4 C A 6 D B 6 E B

Activity Immediate Predecessor(s) Time (Days)
A --3
B A 4
C A 6
D B 6
E B 4
F C 4
G D 6
H E, F 8
a. Draw the AON (activity on node) project network diagram.
b. Calculate ES, EF, LS, LF, and Slack for each activity using the project activity nodes on the AON project network diagram.
c. What is the project completion time?
d. Identify the critical path