Question: 3 9 6 0 While facilitating PI Planning readiness activities, the Release Train Engineer ( RTE ) notices a Feature that is risky to the
While facilitating PI Planning readiness activities, the Release Train Engineer RTE notices a Feature that is risky to the teams because the technology is new. What is one method the RTE can use to reduce this risk?
Make sure all the technical specifications are written before PI execution
Ensure engineering managers are directing the development process
Coach the teams to create exploration Enablers
Ask for a presentation of a detailed design before the PI Planning meeting