Question: 3 . 9 Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: table [
Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows:
tableACTIVITYtableTIME INHOURStableIMMEDIATEPREDECESSORSABCADB CEB CFDGE F
a Draw the project network using AON