Question: 3 ) A company decides to plan a project, with activities, precedence relations and random duration statistics given in the following table: Activity Immediate Predecessors
A company decides to plan a project, with activities, precedence relations and random duration statistics given in the following table:
Activity Immediate Predecessors Duration Minimum weeks Duration Mode weeks Duration Maximum weeks
A none
B A
C A
D B
E B C
F B
G D E
H F G
Answer the following questions:
What method should be used? Compute the mean and variances for each activity and add them to the table above.
Draw the project network and label the arcs with the activity name.
Assuming that the critical path is ABPEGH compute the probability that this path duration is between weeks and weeks.
Assuming that the critical path is ABPEGH compute the number of weeks within which the project will be completed with probability
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock