Question: 3. A consulting engineer is currently evaluating four different proje ts for the future worth of costs, Department of Housing and Urban Development. The benefits,

3. A consulting engineer is currently evaluating four different proje ts for the future worth of costs, Department of Housing and Urban Development. The benefits, disbenefits, and cost savings is shown. The interest rate is 10% per year, compounded continuously. Determine which of the projects, if any, should be selected, if the projects are (a) independent and (b) mutually exclusive Project ID Good Better Best Best of All FW of first costs, 10,000 8,000 20,000 14,000 FW of benelits, $ FW of disbenctits, $ 6,000 1,000 20,000 32,000 FW of cost savings, $ 1,500 2,000 16,000 3.000 15,000 11.000 25.000 42,000