Question: 3. a. Determine the critical path and the early completion time in weeks for the project. b. For the data shown, reduce the project completion
3. a. Determine the critical path and the early completion time in weeks for the project. b. For the data shown, reduce the project completion time (crash) by three weeks. Assume a linear cost per week shortened, and show, step by step, how you arrived at Hint: Create 2 columns: Time Available to Crash and Incremental Crash Cost. Use the formula NT - CT to determine "Time Available to Crash". To determine the Incremental Crash Cost, use the formula (CC - NC)/Time Available to Crash. This will tell you the cost/week to crash each activity
Step by Step Solution
There are 3 Steps involved in it