Question: 3. A project whose critical path has an estimated time of 820 days with a variance of 225 has a 20% chance that the project
3. A project whose critical path has an estimated time of 820 days with a variance of 225 has a 20% chance that the project will be completed before which day (rounded to the nearest day)? (SHOW ALL CALCULATIONS.)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts