Question: A project whose critical path has an estimated time of 820 days with a variance of 225 has a 20% chance that the project will

A project whose critical path has an estimated time of 820 days with a variance of 225 has a 20% chance that the project will be completed before which day (rounded to nearest day)?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!