Question: 3) A software development rm has undertaken a project for government. The system analyst in charge of the project has decomposed the tasks into the

3) A software development rm has undertaken a project for government. The system analyst in charge of the project has decomposed the tasks into the following stages: Activity Immediate Usual Time Crash Time Cost per predecessors month