Question: 3) A software development firm has undertaken a project for government. The system analyst in charge of the project has decomposed the tasks into the

3) A software development firm has undertaken a
3) A software development firm has undertaken a project for government. The system analyst in charge of the project has decomposed the tasks into the following stages: Activity Usual Time Crash Time Cost per month $1,000 $800 A B 5 8 Immediate predecessors None A A B B, C B, C D, E F, G 3 5 6 6 D E F 6 6 8 10 6 8 6 4 $1,200 $900 H 1 1 d. (2 points) Suppose that it costs $1,500 per month to run the project. Formulate a linear program to determine the cheapest way to complete the project in 24 months or less