Question: 3 A stakeholder wants you to create a chart with a granular breakdown of each task and the time remaining to complete the tasks. What
3 A stakeholder wants you to create a chart with a granular breakdown of each task and the time remaining to complete the tasks. What type of chart can you present to them? 1 point Burndown chart Project status report Gantt chart Roadmap