Question: 3. Based on the schedule would you recommend that G&E pursue this contact? Why? Include a one-page Gantt chart for the stadium schedule. ID Activity
3. Based on the schedule would you recommend that G&E pursue this contact?
Why? Include a one-page Gantt chart for the stadium schedule.
ID
Activity
Duration (days)
Predecessor(s)
1
Baseball Stadium
2
Clear stadium site
70
-
3
Demolish building
30
2
4
Set up construction site
70
3
5
Drive support piling
120
2
6
Pour lower concrete bowl
120
5
7
Pour main concourse
120
3,6
8
Install playing field
90
3,6
9
Construct upper steel bowl
120
3,6
10
Install seats
140
7,9
11
Build luxury boxes
90
7,9
12
Install jumbo Tron
30
7,9
13
Stadium infrastructure
120
7,9
14
Construct steel canopy
75
10
15
Light installation
30
14
16
Build roof supports
90
6
17
Construct roof
180
16
18
Install roof tracks
90
16
19
Install roof
90
17,18
20
Inspection
20
8,11,13,15,19
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock