Question: 3. Based on the schedule would you recommend that G&E pursue this contact? Why? Include a one-page Gantt chart for the stadium schedule. ID Activity

3. Based on the schedule would you recommend that
3. Based on the schedule would you recommend that G&E pursue this contact?
Why? Include a one-page Gantt chart for the stadium schedule.
ID
Activity
Duration (days)
Predecessor(s)
1
Baseball Stadium
2
Clear stadium site
70
-
3
Demolish building
30
2
4
Set up construction site
70
3
5
Drive support piling
120
2
6
Pour lower concrete bowl
120
5
7
Pour main concourse
120
3,6
8
Install playing field
90
3,6
9
Construct upper steel bowl
120
3,6
10
Install seats
140
7,9
11
Build luxury boxes
90
7,9
12
Install jumbo Tron
30
7,9
13
Stadium infrastructure
120
7,9
14
Construct steel canopy
75
10
15
Light installation
30
14
16
Build roof supports
90
6
17
Construct roof
180
16
18
Install roof tracks
90
16
19
Install roof
90
17,18
20
Inspection
20
8,11,13,15,19
Question 2: The G&E Company is preparing a bid to build the new 47,000 seat Greendale baseball stadium. The construction must start July 1, 2017, and be completed in time for the start of the 2020 season. A penalty clause of $100,000 per day of delay beyond May 20, 2020, is written into the contract. Ben Keith, the president of the company, expressed optimism at obtaining the contract and revealed that the company could net as much as $2 million on the project. He also said if they are successful, the prospects for future projects are quite good since there is a projected renaissance in building classic ball parks with modem luxury boxes. Given the information provided in the following table, construct a network schedule for the stadium project and answer the following questions: (8.5 points) 1. Will the project be able to be completed by the May 20 deadline? How long will it take? 2. What is the critical path for the project? 3. Based on the schedule would you recommend that G&E pursue this contact? Why? Include a one-page Gantt chart for the stadium schedule. ID Activity Duration (days Predecessors I Baschall Stadium 2 Clear stadium site 30 70 120 3 Demolish building 4 Setup construction site 5 Drive support piling 6 Pour lower concrete bowl 7 Pour main concourse 8 Install playing field 9 Construct upper lo 10 Install seats 11 Build luxury buses 12 Install jumbo Tron 13 Stadium infrastructure 14 Constructe canopy 15 Light installation 16 Build roof supports 17 Construct roof 18 Install roof tracks ###ass="#%%%% 90 7,9 7.9 30 120 75 30 90 6 16 19 Install roof 90 16 17.15 8.11.13.15.39 20 Inspection 20

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!