Question: 3. Complete in draw.io and insert in MS Word. Given the below activities Draw a PERT Diagram and state the critical path and its timing.

 3. Complete in draw.io and insert in MS Word. Given the

3. Complete in draw.io and insert in MS Word. Given the below activities Draw a PERT Diagram and state the critical path and its timing. (24 marks) Duration 5 4 Activity A Conduct Interviews B Administer Questionaires C Read Reports D Analyze Data flow E Perform Analysis F Prepare proposal G Present Proposal Predecessor None None A B,C B,C DE E,F 8 3 4 2