Question: 3. Consider Figure 1, Network Diagram. All duration estimates or estimated times are in days. A B 16 17 14 D E F Start 9

3. Consider Figure 1, Network Diagram. All

3. Consider Figure 1, Network Diagram. All duration estimates or estimated times are in days. A B 16 17 14 D E F Start 9 12 11 End G H 11 Figure 1: Network Diagram a) i. The above network diagram has five paths. List all the FIVE (5) paths. (5 marks) ii. Determine the critical path for this project. (1 marks) b) Calculate the total float for the critical path. (2 marks) c) Calculate the Late Finish (LF) of Activity D. (2 marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!