Question: 3. Consider Figure 1, Network Diagram. All duration estimates or estimated times are in days. Start A 15 D 9 G 8 B 17
3. Consider Figure 1, Network Diagram. All duration estimates or estimated times are in days. Start A 15 D 9 G 8 B 17 12 H E 9 14 F 11 11 End The above network diagram has five paths; the paths and their duration Path 1: Start -> A -> B -> C-> End, duration: 46 days. Path 2: Start >D -> E ->F -> End, duration: 32 days. Path 3: Start -> D -> B -> C > End, duration: 40 days. Path 4: Start -> G ->H ->I -> End, duration: 28 days. Path 5: Start -> G -> E ->F -> End, duration: 31 days. a) Determine the critical path for this project. b) Calculate the total float for Path 4. c) Calculate the Early Start (ES) and Early Finish (EF) of Activity C. d) Calculate the Late Start (LS) of Activity E.
Step by Step Solution
There are 3 Steps involved in it
a To determine the critical path for this project we need to find the path with the longest duration ... View full answer
Get step-by-step solutions from verified subject matter experts
