Question: 3. Consider the following table including the activities of developing new production line: (12) Activity Description Predecessors Time (Hours) 1 Preventive maintenance 3 2 T

3. Consider the following table including the
3. Consider the following table including the activities of developing new production line: (12) Activity Description Predecessors Time (Hours) 1 Preventive maintenance 3 2 T Running devices 1 2 3 Production 1&2 7 4 Process control 3 8 5 Process improvement 3&4 2 6 Final product control 5 2 NNON au A) Draw the network for this project B) Obtain the critical path and its duration C) Calculate ES and EF