Question: please use same values as given and solve completly with forlmulas. thanks 3. Consider the following table including the activities of developing new production line:

please use same values as given and solve completly with forlmulas. thanks please use same values as given and solve
3. Consider the following table including the activities of developing new production line: (12) Activity Description Predecessors Time (Hours) 1 Preventive maintenance Running devices 1 2 Production 1&2 7 4 Process control 3 8 5 Process improvement 3&4 6 Final product control 5 2 | au NN I A) Draw the network for this project B) Obtain the critical path and its duration C) Calculate ES and EF