Question: 3. Consider the information about a project plan presented in the following table. The following table shows the weekly control reports for the first two

 3. Consider the information about a project plan presented in the

3. Consider the information about a project plan presented in the following table. The following table shows the weekly control reports for the first two weeks (assume 5 working days per each week). a) Use the earned value approach to calculate the cost variance, schedule variance, cost performance index, schedule performance index for the whole project at the end of week 1 and at the end of week 2 . b) Use the original estimate approach (budgeted cost) and the revised estimate approach to calculate the projected total cost at completion, respectively at the end of week 1 and at the end of week 2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!