Question: 3. Consider the network described in the table below. (12) Preceding -- Activity L M N Duration 8 3 7 3 0 L L, M

3. Consider the network described in the table

3. Consider the network described in the table below. (12) Preceding -- Activity L M N Duration 8 3 7 3 0 L L, M N O P Q 6 W a. Draw the network diagram. b. Calculate the ES, EF, LS, LF, and Slack for each activity. c. What is project completion time