Question: 3 Continuing with the app-development project scenario from the previous question, which three of the following task relationships demonstrate an internal dependency? Clients must sign
3 Continuing with the app-development project scenario from the previous question, which three of the following task relationships demonstrate an internal dependency? Clients must sign off on the design before the official launch. Partner agencies must deliver image assets before the app is complete. Developers must fix bugs before the Quality Assurance team begins testing. Researchers must conduct usability tests before the team can improve the design. Designers must complete wireframes before they begin prototyping