Question: 3 . Find the critical path ( s ) from the information in the table. Identify the critical path ( s ) and the number
Find the critical paths from the information in the table. Identify the critical paths and the number of days the critical paths isare Activity A B C D E F G H I Days Predecessor A A A B B D C F G E H