Question: 3. Given the following information for a process, the process flow time would be: Activity Flow Time Preceding Task A 10 min None B 6

3. Given the following information for a process,
3. Given the following information for a process, the process flow time would be: Activity Flow Time Preceding Task A 10 min None B 6 min 12 min A D 8 min B E 4 min C F 5 min D, E a. What is the critical path? b. How many minutes will this project take? If activity C is crashed by 3 minutes, how many minutes will the project take? C