Question: 3 hours deadline help please HOMEWORK #4 The following project is at the end of its sixth week. Find the cost variance (CV), schedule variance

3 hours deadline help please

3 hours deadline help please HOMEWORK #4 The

HOMEWORK #4 The following project is at the end of its sixth week. Find the cost variance (CV), schedule variance (SV), time variance (TV) and three indexes. Also find the BAC, ETC and EAC for the project. Is this project favorable or not, please comment. Use the proportionality rule for your calculations. ACTIVITY BUDGET ($) PRE- DECESSORS B D E DURATION (WEEKS) 2 3 3 5 4 ACTUAL COST ($) 380 480 400 150 0 250 500 300 600 400 % COMPLETE 100 100 100 40 0 A . B,C

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!