Question: Question 1 Earned Value Management Question 1 (a) --- Project 1 - 25 marks You are managing a project that is scheduled to take 12
Question 1
Earned Value Management
Question 1 (a) --- Project 1 - 25 marks
You are managing a project that is scheduled to take 12 months to complete and has a budgeted actual cost (BAC) of $1,000,000.
At the Status Date, the project has the following characteristics:
- Planned value (PV) $300,000
- Actual cost (AC) $350,000
- Percentage of work completed 25%
Calculate the following quantities:
- Earned Value (EV)
- Cost Variance (CV)
- Schedule Variance (SV)
- Cost performance index (CPI)
- Schedule performance index (SPI)
Using your results, apply the three (3) formulae listed in calculation of the Estimate at Completion (EAC) of the project.
These formulae are as follows:
- EAC = AC +(BAC-EV)
- EAC = BAC/CPI
- EAC = AC + [(BAC-EV)/(CPI*SPI)]
EAC=AC + (BAC EV)
EAC=BAC/CPI EAC= AC + [(BAC-EV) / (CPI x SPI)].
For each of these calculations, calculate the To-Complete
Performance Index (TCPI).
Question # 2
Question 1 (b) --- Project 2 - 25 marks
You are managing a second project that has the same time and cost specifications as those in Question 1, but which is 40% complete at the Status Date, when Actual Costs are $350,000.
Its specifications are below
- Budgeted Actual Cost (BAC): $1,000,000.
- Schedule time to complete: 12 months
- Planned value (PV) $300,000
- Actual cost (AC) $350,000
- Percentage of work completed 25%
Calculate the following quantities:
- Earned Value (EV)
- Cost Variance (CV)
- Schedule Variance (SV)
- Cost performance index (CPI)
- Schedule performance index (SPI)
Using your results, apply the three (3) formulae listed in calculation of the Estimate at Completion (EAC) of the project.
These formulae are as follows:
- EAC = AC +(BAC-EV)
- EAC = BAC/CPI
- EAC = AC + [(BAC-EV)/(CPI*SPI)]
EAC=AC + (BAC EV)
EAC=BAC/CPI EAC= AC + [(BAC-EV) / (CPI x SPI)].
For each of these calculations, calculate the To-Complete
Performance Index (TCPI).
Question # 3
Briefly discuss 2 main advantages and disadvantages of
- EVM
- NPV
- PV
- FV
- TCPI
- Forecasting
- Payback period
- IRR
- CBR
- BCR
- Depreciation.
Question # 4
Explain the definitions of
- Direct cost
- Indirect cost
- Fixed cost
- Variable cost
- Opportunity cost
- Sunk cost
note = please give me the answer to all questions especially briefly explain questions 3and 4.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
