Question: 3. If a company is working under a certain lead time schedule what is the reorder point for the following information? a. Lead Time =42

3. If a company is working under a certain lead

3. If a company is working under a certain lead time schedule what is the reorder point for the following information? a. Lead Time =42 hours b. Demand =30 per hour *42=1,260 units 4. What would the new reorder point be if the company adds a 3 hour safety stock for this item? 603=