Question: Description Activity a m b Activity Predecessor A 3 5 7 -- B 4 8 10 A C 2 3 5 A D 6 9
| Description |
|
|---|
Using Table ZZ, the critical path for the project consists of activities
| A. | A-B-C-D-E.
| |
| B. | A-B-C-E.
| |
| C. | A-B-D-E.
| |
| D. | A-B-C-D.
|